unable to sert schedule trigger

Posted: Mon May 13, 2013 2:00 am
by KevinU
set schedule for
00:30:00
monthuly on 15th effective 01/06/2013

wont set says never

cange toweekly mon wed fri insted woks

trird on other pc same result

any ideas please

Re: unable to sert schedule trigger

Posted: Mon May 13, 2013 7:41 am
by Oleg
Thank you for the report
Maybe this is incorrect displaying only, because the trigger recomputes next start periodically.

We will recheck this.

Re: unable to sert schedule trigger

Posted: Mon May 13, 2013 8:31 am
by KevinU
days 1 - 13 display k
all the restt how never , inc last day

hope this helps

Re: unable to sert schedule trigger

Posted: Mon May 13, 2013 8:54 am
by Oleg
The "Scheduler" trigger calculates next scheduled time only within next 31 days.
If next "time point" is later than 31 days (after current time) then it writes "never".

Maybe "never" is incorrect word.
Probably it's necessary to change it to "next month" or "not in nearest month"

The trigger works correctly.

Re: unable to sert schedule trigger

Posted: Mon May 13, 2013 9:41 am
by KevinU
how about
'next schedue due ...{date}

asyou may need to shedule qtrly job and it would give user valid info rather than 'next month'